PJ2T Outside Maintenance Plan
Definitions - "Outside Maintenance"
encompasses ongoing care of all of the station components that are outside
of the house, including towers, antennas, feedlines, rotors, radials, cabling,
switchboxes, and transformers. "Ongoing care" includes rust and
corrosion control, periodic inspections, and replacement of broken components.
(Upgrades, such as addition of antennas, are NOT considered maintenance.)
Tower Scraping and Painting Schedule and
Record of Work
Legend: "H" = Herko (contractor),
"Z" = WB9Z, "CG" = W0CG, "CCC" = Club members in
general. Tower sections are numbered from the top down. Greyed
out means completed. Green shows the date
each section was actually done.
|
Eur
10 |
Eur
9 |
Eur
8 |
Eur
7 |
Eur
6 |
Eur
5 |
Eur
4 |
Eur
3 |
Eur
2 |
Eur
1 |
US
8 |
US
7 |
US
6 |
US
5 |
US
4 |
US
3 |
US
2 |
US
1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jan
2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Feb
2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CG |
CG |
CCC |
CCC |
| Mar
2007 |
|
|
|
|
|
|
|
|
CCC |
CCC |
Z |
Z |
CG |
CG |
|
|
|
|
| Apr
2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| May
2007 |
H |
H |
H |
H |
H |
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jun
2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jul
2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Aug
2007 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Sep
2007 |
25th
Ivory
H |
25th
Ivory
H |
25th
Ivory
H |
26th
Ivory
H |
26th
Ivory
H |
|
|
|
|
|
|
|
|
|
26th
Ivory
CG |
CG |
|
|
| Oct
2007 |
|
|
|
|
|
|
|
|
CCC |
CCC |
|
|
24th
Ivory
CG |
24th
Ivory
CG |
|
24th
Ivory
CG |
|
|
| Nov
2007 |
H |
H |
H |
H |
H |
|
|
|
|
|
CG |
CG |
|
|
|
|
CCC |
CCC |
| Dec
2007 |
|
|
|
|
|
Z |
Z |
Z |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jan
2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Feb
2008 |
|
|
|
|
|
|
|
|
15th
Ivory
(N1ZZ) |
15th
Ivory
(N1ZZ) |
|
|
|
|
CG |
CG |
CCC |
CCC |
| Mar
2008 |
|
|
|
|
|
22nd
Ivory
CG |
23rd
Ivory
CG |
27th
Ivory
CG |
CCC |
CCC |
14th
Ivory
Z (CG) |
14th
Ivory
Z (CG) |
CG |
18th
Ivory
CG |
|
|
|
|
| Apr
2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| May
2008 |
H |
H |
H |
H |
H |
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jun
2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jul
2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Aug
2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Sep
2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CG |
CG |
|
|
| Oct
2008 |
|
|
|
|
|
|
|
|
CCC |
CCC |
|
|
CG |
CG |
|
|
|
|
| Nov
2008 |
H |
H |
H |
H |
H |
|
|
|
|
|
CG |
CG |
|
|
|
|
CCC |
CCC |
| Dec
2008 |
|
|
|
|
|
Z |
Z |
Z |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jan
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Feb
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CG |
CG |
CCC |
CCC |
| Mar
2009 |
|
|
|
|
|
|
|
|
CCC |
CCC |
Z |
Z |
CG |
CG |
|
|
|
|
| Apr
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| May
2009 |
H |
H |
H |
H |
H |
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jun
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Jul
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Aug
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Sep
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CG |
CG |
|
|
| Oct
2009 |
|
|
|
|
|
|
|
|
CCC |
CCC |
|
|
CG |
CG |
|
|
|
|
| Nov
2009 |
H |
H |
H |
H |
H |
|
|
|
|
|
CG |
CG |
|
|
|
|
CCC |
CCC |
| Dec
2009 |
|
|
|
|
|
Z |
Z |
Z |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(c:\ham\ccc\stationcommittee\pj2toutsidemaintenance\pj2t.tower.painting.schedule.xls)
Concepts and Assumptions
- Europe and US/JA towers require recoating
roughly every six months.
- The PJ9JT tower is aluminum and requires so
little care that it is not in this plan.
- Member painting is scheduled to coincide with
contests so that no extra trips are required.
- CCC members (not W0CG or WB9Z) who happen to
be on site at the right times will maintain the bottom two sections of both
towers.
- CCC climbers W0CG and WB9Z will do modest
mid-height painting, no more than two to three sections per trip to Curacao.
- The contractor will be used to do the high,
most difficult work and to paint in the season when no hams are around.
- This schedule minimizes use of the expensive
contractor. We can't afford to have him do everything.
- Costs for paint, sandpaper, brushes, gloves,
spray coating, tape, duct seal have all been adequately covered from normal
Station Support money and that can continue.
- The calculations that follow are bare bones,
just enough to keep us in operation. If we could raise more, that would be
desirable but not necessary.
Cost Calculations
- Europe sections 10, 9, 8, 7 and US/JA sections
8, 7, 6, 5 each require 1.5 hours to scrape, 1.5 hours to paint.
- Europe sections 6, 5, 4, 3, 2, 1 and US/JA
sections 4, 3, 2, 1 each require 1.0 hours to scrape, 1.0 hours to paint.
- Contractor total annual hours = (4*3) + (4*2)
+ (4*3) + (1*1) = 33 hours
- At contractor rate of NAfl 100/hour for Herko
($58/hour), annual cost is (33*58) = $1914.
One Time 2006 Cost
We need assistance from Herko and his helper to
get the big antennas down and back up with minimal disruption to contesting.
Four full Saturdays will be needed.
- Per day 8 hours climber @ $58 + 8 hours ground
helper @ $20 = $624.
- Four Saturdays = $2496.
Possible Funding Sources
- Seed the outside maintenance fund initially
via a fund drive. There may be members who would like to make specific cash
donations to the OM fund.
- Add an additional annual dues assessment
specifically for the OM fund.
- Add an additional component to the
"Rent" specific to the OM fund.
- A one-time drive to fund the four Saturdays
would need to raise about $140/member.
- Combinations to raise our annual target of
$1914 include (assumes 18 members and 8 annual rentals):
- OM Annual Dues $50, OM Rent Charge $100
raises $1700
- OM Annual Dues $25, OM Rent Charge $200
raises $2050
- OM Annual Dues $75, OM Rent Charge $50
raises $1750
- OM Annual Dues $0, OM Rent Charge $200
raises $1600
- OM Annual Dues $100, OM Rent Charge $0
raises $1800
- I believe the most painless and most fair
combination would be to make the users pay the most that most member
visitors consider the rent amount to me almost trivial (especially for a
group contest), thus that the second alternative would be best.
- The $600 initiation fee for any new members
could be redirected into the OM fund.
- CCC Board would have the authority to transfer
funds from SS into OM if necessary.
How to Decide
Should we present these alternatives to the
members and let them vote on the most acceptable option?